NETWORKDAYS: working days between two dates

The reverse question: not when it ends, but how many working days it took.

Task:

For each project in the log, count the working days from start to finish, both included. Put the counts in D2:D5.

Interactive Spreadsheet

Hints

+5 XPno-hints bonus

Solve it on your own to keep the bonus. Each hint gets one step closer to the formula.

The data in this exercise

This is the grid you start with. Cell references in the task — B6, C2 — point at the row numbers and column letters below.

5 rows × 4 columns4 cells you fill in
ABCD
1ProjectStartFinishWorking days
2Website3/4/20243/15/2024
3Audit3/11/20243/11/2024
4Move3/8/20243/12/2024
5Launch4/1/20244/30/2024
What this exercise teachesMay contain the answer

Subtracting the dates counts calendar days and excludes one end, so a two-week project reads as 11. NETWORKDAYS counts the days people actually worked, which is the figure resourcing and billing need.